Northeast & Southwest Alabama Construction Effort 3

Statement of Condition of Work from York Station to Bigbee River  Section 28 to 46

October 1st 1862

No. of Section & Style of Work Length of Bridges & Trestles Names of Contractors Proportion of Cast to be Paid Estimated Work done to date Total Done Remaining Work Remarks
Value of Work To be paid for in Paid for in Amount reserved in To be paid for in Total to be done
Cash Stock Bonds Cash Stock Bonds Cash Stock Bonds Cash Stock Bonds
29, 30 & 31   D. H. Trott 50 prct $10000 $5000 $5000   $3845 $2315     $1538   $7698 $1151 $1151   $2302  
32   G.Joimer 100 " 1153 1153     1153           1153         Completed
33   M. McGee 50 " 10106 5053 5053   4085 2450     1631   8166 970 970   1940  
34 & 35   S. M. Potts Stock 9140   9140     6650     1660   8310   830   830  
36   J. P. Rommard " 9760   9760     5435     1361   6796   2964   2964  
37 (1st Part)   H. H. Harris " 2256 50 2500   56 2500         2556         Completed
37 (2nd ")   H. H. Harris 80 prct 1798 1438 360   1438 360         1798         "
38 & 39   James Harris Stock 8000   8000     5880     1466   7346   654   654  
39 (2nd Pt) & 40   R. F. Houston " 6650   6650     6650         6650         Completed
41 (1st Part)   R. F. Houston 90 prct 3422 3080 342   3080 342         3422         "
41 (2nd ")   M. C. Houston " 4977 4480 497   4480 497         4977         "
41 (3rd ")   Hadley & Cuckwell 50 " 8145 4073 7072   4073 4072         8145         "
42   M. E. Houston Stock 12653   12653     12653         12653         "
43   J. H. Brown 2/3 Cash 51000 34000 17000   32020 6400     9608   48028 1980 992      
44   J. M. Gould 90 prct 8314 7483 831   7483 831         8314         Completed
45 & 46   M. C. Houston " 27261 24535 2726   24535 2726         27261         "
Bridge Abutments   Houston & Jones 90 " 10712 9641   1071 9641   1071       10712         "
Bridges 108' Scotts & Adams 50 " 4170 2085   2085 402   402       804 1683   1683 3366  
Trestling   Scotts & Adams " 15626 7813   7813               7813   7813 15626  
Cross Ties   Scotts & Adams " 24354 12177   12177               12177   12177 24534  
Land Damages       3160 3160     654           654 2506     2506  
Miscellaneous       600 600     100           100       500  
???       2810 2810     2810           2810          
      Totals 236367 128637 84584 23146 99855 59761 1473   17264   178353 28780 7561 21673 58014  
     

Necessary to complete from Section 28 to 46 = 19 Miles

        $28,780 $7,561 $21,673 $58,014  
     

Add reserved percentage

          17,264   17,264  
                              $28,780 24,825 21,673 78,278  