Long before the war, railroad men had seen the advantages to be
had from a single line of connected roads from Richmond to New
Orleans/Vicksburg. The common route was to be as straight as
possible, while hitting all the main population and railroad
centers on the way. The dream route was as follows: Richmond,
Danville, Charlotte, Columbia, Augusta, Macon, Montgomery,
Jackson and then south to New Orleans or continue west to
Vicksburg – and then to Shreveport and on to the Southern
Pacific Railroad. Gaps existing in this route when the war began
were some of those that received attention for immediate
construction – the Piedmont Railroad, the Columbia & Augusta
Railroad, the Milledgeville Railroad, the Montgomery & Columbus
Railroad and the Selma & Meridian Railroad. The Piedmont
Railroad and the Selma & Meridian Railroad were crucial to the
support of Richmond and major armies and got first attention.
Lack of labor and iron caused the remaining roads to flounder
and languish until late in the war, when additional and
alternative routes became most important. Labor and iron was
still lacking, but interest had picked up. |
The Columbia & Augusta Railroad was probably the most important
railroad that the Confederacy did not complete. The existing
route required a sixty-four mile run south to Branchville, then
reverse direction and head seventy-five miles northwest to
Augusta. This strange route was the result of the South Carolina
Railroad being built to suck inland freight to Charleston, not
to connect with neighboring states. The proposed straight line
connection would be about seventy miles long, saving seventy
miles in freight charges and about eight hours in time. The
obvious secondary benefit was the continuation of travel from
Augusta to Charlotte if Branchville or Charleston should be lost
to the railroad network by Union capture or destruction. This
internal line, remote from enemy interference, was the same
argument that had been used, successfully and correctly, for the
Piedmont Railroad project. |
The Columbia & Augusta projected benefitted from three factors:
the new road required no significant bridges, the route would
mostly be on a ridge top and therefore required less filling and
embankments, and the last eleven miles could be run on existing
South Carolina Railroad track. Additional, unspoken, benefits of
this route would be that slaves that had been sent inland for
safety could be used on the work, and the country had not been
damaged by enemy raids. The projects drawbacks were the usual –
lack of labor and lack of iron. |
William Johnston was a highly respected railroad president. He
set high standards for his railroads, and achieved them. He was
an efficient manager, able to take the debt-saddled Charlotte &
South Carolina Railroad and bring it back to full solvency, then
built the Atlantic, Tennessee & Ohio Railroad – without state
aid or debt. He was the obvious man to extend his two roads
south from Columbia to Augusta. Johnston had been involved with
this project before the war and in his January 1, 1863 annual
report to the Charlotte & South Carolina stockholders he noted
their readiness to resume the project whenever the people of
Augusta, Columbia and the planters between the two were ready to
step up to the task. |
It is unfortunate for our story that there were few central
government documents generated by the construction project and
the state ones were apparently lost with the destruction of
Columbia. Regardless, the bare outline of the project can be
determined. Newspapers in the area mentioned the need to restart
the construction in March and June, 1863. Without any additional
documents, it is clear from newspapers that books for
subscriptions for stocks opened in various cities and towns in
early July; the response was quick and complete. By August 10th,
enough stock had been subscribed to allow the company to
organize and call its first meeting. By the 13th, the
meeting had been held and Johnston elected President; James G.
Gibbs (or Gibbes) was selected as Chief Engineer. |
On October 9th, Engineer Gibbs advertised for bids
for the grading and masonry work on the first twenty miles,
starting at Columbia. Bids would close on November 10th,
with the profiles and specifications available in the company
office, in Columbia, after October 25. He optimistically noted
that the company would probably be able to furnish most of the
tools necessary. |
December 18th saw the company call for the rest of
the subscription payments, with 35% due January 1, 1864 and the
balance, 25% on February 1. It appears that the company had a
name change on January 1, from Columbia & Hamburg to Columbia &
Augusta Railroad. Hamburg was the first destination of the South
Carolina Railroad when it was constructed, but it had not become
the center of commerce that Augusta had, so the name change
recognized the greater importance of Augusta. |
On January 18, 1864, President Johnston wrote Secretary of War
Seddon regarding the status of the project and to ask for
assistance. He stated that the entire route would be located by
the end of the month and offered to contractors. He noted that
the confusion regarding the currency was causing the road to
delay letting contracts and hoped the government would settle
the currency issue. He then asked that Major Melton, Chief of
Construction of the State of South Carolina, be allowed to grant
exemptions from military duty for up to forty contractors who
would obligate themselves to each work not less than twenty
slaves on grading the road, getting crossties and constructing
bridges. He asked, further, that rations and clothing for the
slaves be provided through Government’s agents so that the
government and the railroad would not be bidding against each
other. If the Secretary would not agree to the Government
providing such through its agents, he asked that the company be
given transportation priority equal with the government from
wherever the railroad had to go to purchase the supplies. The
road expected to employ 1,000 to 1,500 hands and would need the
supplies for that number. The Company expected to have the road
graded and some rail laid by August. However, the Company could
not provide the rails and asked the Government to do so. |
Colonel Sims, in replying to a request for comment on another
matter to the Quartermaster General, stated on April 1, said he
could not urge too strongly the need to provide the iron so that
this road could be completed. This comment was in the midst of
several letters, reports and orders in the Richmond area
regarding providing the iron. Unfortunately, none of the
documents has survived. |
On May 1st, the President and Directors held a
meeting in which they authorized the President to go to Richmond
to attempt to speed up the support the road had requested. The
Chief Engineer also made an extensive report, which the Columbia
South Carolinian published, but it too extensive to quote
here. The conclusion was that the route selected was one that
rose to the ridge line just west of Columbia and stayed on it
almost to Hamburg. The route was selected to reduce the grade
the locomotives would have to climb and to reduce the number of
bridges required. The route would be a good one for taping
future business after the war. Most of the road would be about
500 feet above the level where it starts in Columbia. Only
thirteen miles of heavy grading was identified. He estimated 1.1
million cubic yards of excavation and 1.6 million cubic yards of
embankment, 2,000 feet of bridging, 8,000 yards of masonry and
200,000 cross ties. |
Engineer Gibbes projected eight months for a force of 1,000
hands for the grading, with an additional 100 hands on the
bridging and a final 100 getting out the superstructure (mostly
the cross ties). Wooden piers would be used to speed the
construction of the Congree River bridge of such a type that
would allow permanent masonry construction later without
interrupting traffic. |
During the week after the meeting, advertisements are found for
hands and supplies in several newspapers. The numbers are not
large and indicate that each contractor was advertising for the
hands he needed for his own contract. Then came the big call,
with a July 16th ad for 1,000 hands, to start work
promptly. Tools would be furnished by the Company and the
contractors would be detailed by the Secretary of War and all
their supplies would be exempt from impressment. |
Providing engineering supervision may have been a problem. Prior
to starting the work, Johnston had requested a particular
Captain from the Engineer Department, but he was refused. In
mid-May, the principal assistant engineer to Engineer Gibbes was
appointed an Engineer Bureau Captain and ordered to report to
General Lee in Virginia. |
The Editor of the Augusta Constitutionalist noted on
September 29th that he had met with Johnston and
learned that 400 hands were at work on the two ends of the new
road and the planters in the center section were completing the
central portion. He reported again on December 24th
that the road had 560 hand employed, with the whole line under
contract and twenty-five miles graded. More hands were wanted
immediately. The Editor then dove into the question of sourcing
the iron rails. In his opinion (sharpened, not doubt by
Sherman’s army), the Charleston & Savannah Railroad and much of
the Central (of Georgia) Railroad should be taken up immediately
to supply the company. He had been assured that the road could
be completed by March 1st if the South Carolina
Legislature provided the necessary assistance and if they did
not, the Georgia Legislature should provide it. In a separate
article, he pressed the completion of the Milledgeville
Railroad, another segment of that great railroad from Richmond
to the West. |
On October 8, 1864, General Order #77 was issued in Richmond. It
revoked all details that had been granted under authority of the
War Department to men ages 18 to 45 and all such detailed men
were required to assemble at the camps of instruction for
service in the armies. This cost the project many of its
contractors and many of their slaves. |
On December 27th, Johnston wrote Secretary Seddon
that by October he had about 600 hands, with the required
contractors. But despite the General Order, he had still managed
to have 400 hands at work. Then the military authorities at
Augusta took 300 of them to fortify the city. He was still
adding hands and had between 500 and 600 hands at work. The
great difficulty was in getting the contractors, eight or nine
of whom he had managed to get detailed again, and a few older
men. If the War Department would detail or exempt sixty
contractors, he thought he could get 1,500 to 2,000 slaves on
the work and could have both ends of the road ready for rails by
April and the rest of the road could take iron as soon as it
could be had. The road would be seventy-nine miles long, but ten
miles of South Carolina Railroad track would be used near
Augusta, leaving sixty-nine miles of iron needed from the
Government. He proposed taking the iron of the Charleston &
Savannah Railroad or a portion of the South Carolina Railroad
south of Branchville or, if necessary, the entire seventy-five
miles of the Spartanburg & Union Railroad. |
Engineer Bureau Chief Gilmer endorsed the letter of January 2,
1865 that the exposure of the South Carolina Railroad south of
Branchville made it essential that the road should be pushed and
the sixty men details and transportation assistance for
materials should be provided. The South Carolina Legislature
passed a resolution asking the Secretary of War to make
construction of the road a priority. |
Then the record goes silent. Sherman headed north from Savannah
in early January and took Columbia on February 16th.
It seems likely that, as long as the hands could be fed, the
work continued. But laying iron waited until a year after the
war ended. The road accepted traffic in 1867. |
|