Amount of work done by E. L. Ligon on the Shelby Iron
Cos Rail Road
|
Graduation |
4209 |
yds |
E Exca |
@ |
40 cts |
pr yard |
$ |
1,683 |
.60 |
200 |
" |
Loose Rock Exca |
@ |
$1.00 |
" " |
|
200 |
.00 |
24,704 |
" |
Embankment |
@ |
37 1/2 cts |
" " |
|
9,264 |
.00 |
33 |
acres |
Clearing |
@ |
$35 |
" acre |
|
1,155 |
.00 |
|
|
|
|
|
|
$ |
12,302 |
.60 |
Superstructure |
7,000 |
cross ties distributed |
@ |
50 cts each |
$ |
3,500.00 |
|
|
1,000 |
" " in woods |
@ |
25 cts each |
|
250.00 |
|
|
1 |
culvert |
@ |
$75 |
|
75.00 |
3,825 |
.00 |
|
Total amount of work
done |
|
$ |
16,127 |
.60 |
|
|
Less 20 pr cent |
|
|
5,225 |
.52 |
|
|
|
|
|
|
$ |
12,902 |
.08 |
|
|
Less former Estimate |
|
|
5,785 |
.00 |
|
|
Amount due |
|
$ |
7,117 |
.08 |
|
I certify that the above account is just
and correct |
Wm M Wallace |
Chf Engr |
Dec 23rd 1863 |
Shelby Iron |
|