Northeast & Southwest Alabama RR |
Board of Directors Minutes for August 1862 |
|
Stated that 15 miles of track had been laid
between 10/1861 and 7/1862 |
5/25/1861 -- paid for 846 tons of RR iron
imported |
7/26/1861 -- paid $1931 for spikes in
Richmond |
8/X/1862 -- paid Alabama & Mississippi
Rivers RR for 4,000 lbs spikes |