NA, RR 9/4/1863

The Confederate States
Appropriation for Engineer Service
To A. A. Traylor
 
Date Designation Application Cost
Dollars Cts

1863

       

Sept. 4

For hire of Slave Carpenters during the months of July and August 1863, viz.  Construction Appomattox Bridge on charge of Confederate Track    
  Joe   18 days at $3.50 per day   63 00
  Jesse 18    "    "      "     "     "   63 00
  Henry 14   "    "      "     "     "   49 00
  Nathan 15  "    "      "     "     "   52 50
         
      $227 50
 
   I certify that the above account is correct and just.
Chas. H. Dimmock
Capt Engrs
 
   Received at Petersburg Va. this 4th day of September 1863 from Chas. H. Dimmock, Capt Engrs the sum of two hundred & twenty seven 50/100 dollars in full of the above account.
A. A. Taylor