NA, RR 9/15K/1863

The Confederate States
Appropriation for Engineer Services
To Samuel T. Smith
 
Date Designation Application Cost
Dols Cts
1863        
Sept 15 To 17 Caps 12x12, 10 ft. long 2040 ft Bridge over Appomattox River Change of Confederate Track    
   " 34 Parts 10x10, 15   "     "    4250      
   " 34 Braces 10x10, 18 "    "    5100      
    " 27 Sills 12x12, 20   "     "   4080      
    " 59 Pieces 8x14, 31  "     "   17070      
   "  13 Caps 12x12, 10  "     "    1560      
   "  26 Pieces 10x10, 8  "     "    1733      
   "  26 Braces 10x10, 10 "   "    2167      
   "  13 Sills 12x12, 17    "    "    2652      
   "  150 Plank 3x10, 17  "     "   6375      
  Making 47027 ft at 5c per ft.   2351 35
    " 70 Piles at $5.-- & 150 Piles at $8.-- each   1550 00
    "  950 Cross Ties at $1.66 2/3 cts each   1583 33
    "  7 Cords Wood at $10.-- per cord For Steam Pile Driver 70 00
    "  2578 ft -- 2 in. Plank at 5c per ft   128 90
      5683 58
 
   I certify that the above account is correct and just; the articles to be (or have been) accounted for in my Property Return for 3rd quarter of 1863
Chas. H. Dimmock
Capt. Engrs.
 
   Received at Petersburg Va this 15th day of September 1863 from Chas. H. Dimmock Capt Engr the sum of Fifty six hundred & eighty three 58/100 dollars in full payment of the above account.
Saml. T. Smith