To making connection between Central RR &
Sav Albany & Gulf RR Depots by running track through
Liberty St. Savannah |
Dollars |
Cts |
1862 |
For work on grading & laying
track on road |
800 |
00 |
June 10 |
"
1804 cross ties furnished at 35 cts |
631 |
40 |
|
" 78
1/2 Tons RR Iron furn @ $80 pr Ton |
6280 |
00 |
|
"
Spikes & 20 Chairs |
702 |
00 |
|
" 4
Kegs cut Spikes & Nails |
100 |
00 |
|
"
22376 ft lumber for Crossings |
335 |
64 |
|
|
|
|
8849 |
04 |
|
To Central RR Co |
|
|
|
|
|
For Carpenters work as per Mr Mollers Bill |
27 |
50 |
|
|
|
" work on
Grading |
278 |
40 |
|
|
|
To A Schwaab for surveying &
superintending |
200 |
00 |
505 |
90 |
|
|
|
|
9354 |
94 |
|
Above amount to be distributed as follows |
|
|
|
|
|
Amt chd by Sav A & G RR |
8849 |
04 |
|
|
|
To be paid by Sav A & G RR 9354.94 |
4677 |
47 |
|
|
|
Confederate States Government to SA&G RR |
4171 |
57 |
|
|
|
To Central RR |
505 |
90 |
|
|
|
Total to be paid by Confederate S Gov. |
$4677 |
47 |
|
|
|
|
|
|
|
|