NA, RRB 4/15A/1862

Confederate States
To David Bisset
 
1862   Dollars Cts
April 15 To repairing & securing Government Bridge at Petersburg  
  To 31 Quarryman 14 days each @ $1.375 596 75
  To 5 Boat Men     14   "        "        $1.25 87 50
  To 20 Laborers    13   "        "          1.00 260 00
  To   1 Chief Blaster 15 1/4   "          2.00 30 50
   "     1 Foreman     22            "          3.00 66 00
   "        Hire of scow              " 50 00
   " 2000 feet Lumber @ $18 36 00
   " 2000 feet safety fuse @  38 00
   " 4 kegs of powder @ $25 100 00
   " Blacksmith's bill for lussing Tools 65 75
   " My own Supervision one month 150 00
    $1472 50
 
R. S Payt David Bisset
PS. It will be presumed that the price charged for hands includes the use of all tools
Respectfully
D. Bisset