NA, N&C 2/2/1863

Confederate States of America
To Nashville & Chattanooga Rail Road Company
 
1862 For furnishing material and building Trestle Bridge over Duck River in Sept. & Oct. 1862    
7 1/2 Days work Carpenters (Foremen) @ $5.00 $37 50
7    "         "            "               "          "    3.50 24 50
7    "         "            "                           "    3.00 21 00
48 1/2    "         "            "                           "    2.50 121 25
43    "         "            "                           "    2.00 86 00
387 3/4    "         "       Laborers                    "    1.50 581 62
216 1/4    "         "            "                            "    1.25 270 31
22 1/2    "         "            "                            "     1.00 22 50
6    "         "            "                            "       .75 4 50
13    "         "        Hauling                     "     2.00 26 00
6    "         "       Engine and Train       "    30.00 180 00
37825 ft B. M. square timber                      "    15.00 567 57
2100  "     "    lumber for cross ties           "    20.00 42 00
1256 1/2 lbs bolts                                           "          18 cts 226 17
531   "  Rail Road Spikes                        "          15  " 79 65
240   "  cast washers                                "          10  " 24 00
    $2314 37
 
   I certify on honor that the above is a correct account of the expenses for material furnished and labor done rebuilding Trestle Bridge (destroyed by the army over Duck River), in compliance with an order of Major Genl. Saml. Jones, to rebuild such Bridges as had been destroyed on the Nashville & Chattanooga Rail Road, so as to pass trains over them and that the material furnished and work done were necessary for the passage of trains over the Bridge.
R. C. Morris
Rest. Engr.
Office N. & C. R. R. Co.
Chattanooga Febry 2, 1863

Home