The Confederate States, For Fort Morgan
|
To Mobile & Ohio RR. Co A. F. Irwin Tr. |
|
Date |
Designation
|
Application |
Cost |
Nov 15 |
For 528 Bars RR. Iron weighing 112 tons @ $33
per ton {about 53 lbs per yard; about
one mile long, both rails} |
Completion of RR from Fort
Morgan to advanced batteries and Wharf at Navy Cove |
3696.00 |
|
For 40 Kegs RR spikes, wt 6000 lbs @ 7c |
|
420.00 |
|
|
|
|
|
|
|
|
|
|
|
4116.00 |
|
|
Received, Mobile Nov 30, 1861, from Capt.
F. H. Lockett, Corps of Engineers, the sum of Four thousand one
hundred and sixteen dollars and --- cents in full payment of the above
account. |
A. F. Irwin |
Treasr |
M. & O. R. R. Co. |
|