Summary Statement of Work done at Macon Armory, in the
month of November 1864 |
|
Grading & Excavating |
670 cubic yards of earth have been
excavated from cutting for R. Road Siding into Armory Grounds, and used
in grading grounds in front of Armory buildings. |
***** |
{Jas. H. Burton} |
{Superintendent} |
{This multi-page report has no
date, but is assumed to be a month's end, and has no indication of
whether this was a report to Col. Gorgas or was just a memo to the
files; it is not signed} |
|