AR, VC 10/1/1861 E

Annual Report of the Virginia Central RR
as of October 1, 1861,
Engineer's Report
 
Engineer's Report
Engineer's Office Virginia Central Railroad
Staunton, October 1st, 1861
 
E. Fontaine, Esq., President
 
Sir,
   The following report of the Principal Assistant Engineer is respectfully submitted as a statement of the condition of the work between Jackson's river and Covington.
   It will be seen that with the exception of some ballasting, and a small amount of embankment, the road bed is finished and ready for the track.
   The iron work for the bridge over Jackson's river is in progress at the Tredegar works in Richmond, and is expected to be finished as soon as the rails for the track can be transported from Richmond to Jackson's river.
   The amount of other transportation required at this time renders it difficult to say when the rails can be carried; every available car will be used for the purpose, and I hope to commence laying the track by the 1st of January next. The completion of this last section of your road is much to be desired, and especially so at this time, as it would materially reduce the expense of transporting supplies to the western army.
   To the estimate of the amount required to finish the grading and the station buildings at Covington, as stated by Mr. Richardson, should be added the estimate for the iron bridge, and the cost of laying the track as follows:
Amount estimated to complete the grading, &c. $8,508.00
       "            "       for station buildings, &c. 7,000.00
       "            "       for iron bridge 13,000.00
Laying 10 miles of track 4,500.00
Chairs, spikes, &c. 5,200.00
Total estimated cost $38,208.00
   For further particulars, I refer to the report which follows.
Very Respectfully,
Your obedient servant
H. D. Whitcomb
Chief Engineer
 
Staunton, Va., October 1st, 1861
 
H. D. Whitcomb, Esq.
Chief Engineer and General Superintendent
 
Sir,
   I here report to you the condition of that portion of the Central Railroad yet under construction, viz: Jackson's river depot to Covington. Two extraordinary causes have operated during the past season to prevent the completion of this work at the time you anticipated in your report in October, 1860. The war has with drawn some of the force engaged on the work, and it is but a natural consequence, in such times as these, that many obstacles would intervene to prevent the completion of the road with the facility that ordinary times would allow. The other cause is the unusual amount of rain, which, in many cases, came with violence, and the high water had a serious effect on the newly made embankments, and in some instances the cuttings suffered from the severe washings. Heavy slides have occurred, and are yet liable to occur. The masonry is uninjured, and will evidently remain so. Karnes' creek viaduct withstood a violent flood, which came upon it in such a manner as to test it severely. An arrangement is now being made to carry the water through the arch in a proper direction. The abutments and piers at Jackson's river, on Section 65, were well tested by a flood nearly as high as any ever known there. The masonry for the bridge over the James river canal is done, and at present is buried in the embankment. It is probable that this portion of the railroad, comprising the sections between Jackson's river depot and Covington, will have a much smaller percentage of perishable work on it than any other portion of the road of an equal amount of work. 
   The work now remaining to be done is approximately as follows:
Sec. 59. 1,000 yards earth to repair bank at Alum Rock, at 18 cents $1,800.00
Hauling do., at 7 1/2 cents (500 feet) 750.00
400 yards of ballast at $1 400.00
1,000 yards of Rip Rap at $1.50 1,500.00  

 

   Amount on Section 59 $4,450.00
Sec. 60. Fixing Karnes' Run at viaduct 500.00
2,000 yards earth, borrowed at 20 cents 400.00
500 yards ballast at $1 500.00
   Amount on Section 60 1,400.00
Sec. 61. 1,200 yards earth, borrowed at 20 cents 240.00
100 do. Rip Rap at 60 cents 60.00
400 do. ballast $1 400.00
   Amount on Section 61 700.00
Sec. 62 complete. Final estimate not returned
Sec. 63. 5,000 yards of a slide at 20 cents 1,000.00
Sec. 64. 600 yards of a slide at 18 cents 108.00
Sec. 65. Complete
Sec. 66. Complete
Sec. 67. 200 yards of ballast at $1 200.00
Covington Depot Section, C. & O. Railroad, 1,000 yards slate at 65 cents 650.00
   Amount of grading, &c. $8,508.00
   You will observe that more than half of the work to be done is on Section 59. In September last a very large freshet made a serious inroad upon the embankment along the new channel of the river. The road bed is yet undisturbed, and the ballast in the adjacent cut is only needed to make this section ready for the track. It may yet be expedient to lay the track, and carry the materials for the repair of the embankment by a train.
   It may not be inappropriate here to record that Mr. Isaac Steers, the well known and highly respected contractor, after having nearly completed this important piece of work at Alum Rock, lost his life in the river about three months since during one of the floods. It is but justice to his memory to say, that for some years past he has by his energy, skill and industry, been a valuable man to the Company in building this road.
   Of the buildings at Covington Station I cannot speak definitely. Sites have been prepared for freight, passenger, road and water stations, engine house, and turntable of 45 feet diameter. Lumber is now being delivered for a wooden freight house, 134 by 28 feet, and a wood house 60 by 20 feet. To build the above mentioned stations economically of wood, would probably cost $7,000. Sufficient cross ties are ready to lay the track, and two train loads of iron are delivered. Aside from such cases of delay as I mentioned in the beginning of this report, the track could be laid to Covington in three months.
   I assumed the charge of this work in July last. I am able to say, that the contractors have evinced a disposition to finish the road to the satisfaction of the Company.
   Soon after my taking the work, Mr. A. H. Sheppard, of the engineer corps, was called to another portion of the road; the other members of the corps, Messrs. Jno. F. Jordan, A. S. Kinney, Wm. M. S. Dunn, and Wm. E. Sparrow, are at present engaged in making final estimates, and finishing up all business connected with their departments. Their work is faithfully done.
   All of which is respectfully submitted.
S. A. Richardson
Principal Assistant Engineer

Home