AR, NOO&GW 1/1/1863 L

Annual Report of the New Orleans, Opelousas & Great Western RR
as of January 1, 1863
Land Agent's Report
 
Engineer’s and Land Agent’s Report 
 
A. B. Seger, Esq
Acting President
 
Sir,
   I respectfully submit the following report of the departments under my charge.
   At the date of the company’s last annual report, the roadway graduation from Berwick’s Bay to a point near Vermillionville a distance of about 63 miles -- had been completed, with the exception of half a mile of very light grading across Mrs. Mead’s plantation – on Bayou Teche – and one and a half miles of embankment required across the swamps east of Bayou Sale. In part, the bridges, culverts, cattle-pits and road-crossings needed on this portion of the line had been built, and material procured for continuing their construction. About 11,500 cypress cross-ties – or sleepers – mostly sawed, had been purchased and piled on the west bank of Berwick’s Bay in readiness for the commencement of tracklaying. These ties were a part of a large number – 100,000 – contracted for and then in course of delivery. The Bayou Vermillion bridge abutments – of brick masonry – had been commenced, and an iron bridge for this crossing had been contracted for.
   Early in the spring of 1862, a contract was concluded between the Company and Messrs. Phillips & Gillman, for the graduation – by steam dredging machinery – of the unfinished portion of the swamp east of Bayou Sale. About the time the contractors had completed their preliminary preparations for the commencement of this work the events of the war prevented further proceedings, and nothing whatever has since been done.
   The same cause has, to this time, prevented the further delivery of cross-ties, -- under the contract for 100,000 above referred to, -- and the force employed in procuring them was broken up and dispersed.
   Nothing further has been done towards the completion of the remaining small bridges, culverts, cattle pits and road crossings required between Berwick’s Bay and Vermillionville, including also the bridge masonry at the Bayou Vermillionville, for the same reason.
   Contracts were concluded, in February last, between the Company and Messrs. A. E. Mouton, and John McGinty, for the graduation of the road way from the end of the old work, near Bayou Vermillion, to Opelousas. Work was immediately commenced by both contractors; one beginning at Vermillion and working northwards, the other at Opelousas, working south. The former had about ten miles of moderately light grading through open prairies, mostly cultivated, the latter about twelve miles of rather heavy work, mostly through woodland, comprising the high embankments required across the valleys of the Bayous Carroncro, Bourbeau, Callahan and Tesson.
   At the date of my last visit of inspection of this work, in the later part of May last, both contractors were progressing rapidly and very satisfactorily; several miles having been completed by each contractor. Mr. Mouton was working exclusively with slaves, and McGinty with whites, mostly irish labourers. At this time I arranged to have the clearing completed between Grand Coteau and the Tesson by Mr. McGinty, and by negroes under the management of Mr. Moor, an employee of the Company.
   The interruption of communication between the city and country, which soon afterwards occurred – and which has since continued – incapacitates me from reporting, a fully as is desirable, upon the present state of this work, but I am informed that up to a recent date it was still progressing and well advanced towards completion, under the efficient superintendence of Thomas Kleinpeter Esq’r, Assistant Engineer. The clearing was entirely completed some months ago, and I believe that fully seventeen, of the twenty two miles to be graded, -- and possibly more – have been finished. Our late President, Wm. G. Hewes Esq’r, who was in Attakapas from the early part of summer up to the date of his decease – in August last – gave his personal attention to this work and urgently insisted upon its being continued uninterruptedly to completion. This done, our Company will have a very important division of their road – extending from Berwick’s Bay to Opelousas, eighty five miles, -- ready for tracklaying; the one and a half miles of swamp near Bayou Sale excepted.
   I need not enlarge upon the very great importance of completing the road to Opelousas, for this is fully appreciated by you. Regular and rapid communication between the city and the cotton districts of Attakapas will thus be secured, and the prompt sale, at good prices, of the seventy five to eighty thousand acres of fertile and valuable land – especially adapted for the culture of sugar-cane, cotton or corn – owned by the Company opposite this portion of their line.
   The completion of the graduation to Opelousas will entitle the Company to receive from the State, for the purchase of rails, $510,000 in state bonds, at the rate of $6,000 for each mile graded.
   A company, organized under an Act of the Legislature of 1861-62, has been formed for the purpose of constructing a railway from our line at New Iberia – one hundred and twenty five miles from New Orleans – to the terminus of the railway from Houston, Texas, at Orange, on the Sabine river. Arrangements had been concluded for the location and construction of this important connecting railway at once, but it is not known what progress has been made. In behalf of our Company and under instructions from our late President, I made arrangements for the injunction of the two roads at the site of our New Iberia Station, but the matter was not definitely settled. The completion of this connecting link of railway would place New Orleans in communication with a large part of Texas, by means of the several roads now in operation and radiating from Houston.
   The line of our road from Opelousas to the Sabine river – ninety three miles – was staked out in the summer of 1857. The total distance from Algiers to the Sabine river terminus is two hundred and fifty eight miles. No better point could have been selected for a terminus on and crossing of the Sabine valley than at Thompson’s Bluff, from Burkesville Texas to the Sabine end of our line. A railway thence b y way of Burkeville, San Augustine, Nacogdoches, and on to Dallas will, it is hoped at a not far distant day, connect New Orleans with the great cotton and wheat regions of eastern and northern Texas.
   From Pine Prairie – 190 miles from Algiers – a branch road of twenty miles would connect with the Alexandria railway, in the rich and fertile valley of the Bayou Boeuf, sixteen miles distant from Alexandria on Red river; making the distance from New Orleans to Alexandria 226 miles.
   Profiles of the line of road from Opelousas to the Sabine have been prepared – during the [past year – and estimates made of the earthwork to be done to grade the roadway between said points. A maximum grade of 31-68 feet per mile was assumed for this part of the line, there being no necessity for exceeding this comparatively low limit.
   A “General Reference Map of so much of lower Louisiana and eastern Texas, as is necessary to exhibit the main line of the New Orleans, Opelousas & Great Western Railway from New Orleans to the Sabine River, or eastern boundary of Texas, together with its proposed branch to Red River, extension into northern Texas, connection with southern and western Texas, and the lands belonging to the railway Company” has been carefully and accurately made during the past year. It is suggested that this map, if handsomely engraved, published and circulated, would be valuable to the Company in their future negotiations, and very interesting – as well as useful – to all interested in the truly great work of developing the resources of western and southwestern Louisiana, and of connecting our city, by railways, with the valley of Red River and with northern Texas, and ultimately with Mexico and the Pacific coast.
 
Lands
 
   The New Orleans, Opelousas & Great Western Railroad Company, by and in virtue of an Act of the United States Congress approved June 3d 1856, and an act of the Legislature of Louisiana approved March 16th 1857, received a donation of land, consisting of the alternate odd numbered sections within six miles of their line of road, and all vacant odd numbered sections within fifteen miles of their line if found necessary to supply any deficiency in the grant of six sections per mile within the six mile limits. As the total length of the line of the road is 258 miles, -258X6=1548 sections of 640 acres each, or -990,720, acres were called for by the grant. As only about 705,000 acres of vacant land were found within the entire fifteen mile limits, the grant practically conveyed to the Company all the vacant odd numbered sections included within a strip of territory thirty miles wide, bounded by lines parallel to the railroad line and every where fifteen miles distant there from.
   Though this grant was made in June 1856, it was only in 1861, or five years thereafter, that it became available to the Company. All this time was consumed in defining the grant limits; determining what was vacant and selecting the vacant lands in the District and General Land Officers; preparing and correcting the land lists for final approval, &c. Several other railway companies were the recipients of similar donations in 1856, and all could not be attended to at once. The lists for our Company were, in consequence, postponed to the last. Other companies received their lists and made extensive sales before our lists were transmitted to us; but for the great delay in our case we also might have made large sales and thus have obtained funds for the more rapid prosecution of the work of construction. This is fully evidenced by the fact that up to the 25thof May lat one hundred and eighty six applications had been made to purchase lands from the Company, amounting in the aggregate, to 50,000 acres. It is true that in several cases several parties applied to purchase the same land, but this competition serves to show how active would have been the demand for the Company’s lands but for the intervention of the war. But two sales were made; one tract at $15 and the other for $2.50 per acre, cash. Rapid sales may be anticipated when peace is restored and business is resumed.
   The plan adopted by the Company has been to have each tract of their land carefully examined, and an accurate description of its characteristic made and filed, together with a plat or sketch, in a Land Description Book prepared for the purpose, before fixing the price at which the land will be sold. This undoubtedly occasions some delay in sales, but, as the Company desire to realize all they can from their lands, and to invest the proceeds in the extension of their road, this is not considered objectionable, particularly as the extension and opening of the road adds constantly to the value of the lands unsold. The Company will, of course, avail themselves of the benefits of such increase in value. The early purchases, at the first price fixed by the committee on lands – composed of members of the Board of Directors, appointed by themselves, for the purpose of determining the price at which lands shall be sold – will have the advantage of this increased value, it being well known that the completion and operation of a railway greatly adds to the former values of landed property.
   Many examinations have already been made and reported, but these have, necessarily been discontinued for the present. Prices have been fixed upon nearly all of the tracts so far reported.  
   Advantage was taken of the experience of other land grant companies in determining upon the system to be adopted in conducting this important branch of the Company’s business, and it is believed that the arrangements made are such as will prove to be simple and efficient.
   Books of Registry have been opened and the lands registered therein according to the lowest legal subdivisions; two large folio volumes being filled therewith. Books for Land sales, Descriptions, &c., have also been prepared.
   The engraving, publication and distribution, of the General Reference Map of the whole line of road described in the engineer’s report – showing as it would all the Company’s lands and their locality – would serve admirably as an advertisement of these lands.
   Opposite the first one hundred and twenty five miles of the line of road, the lands owed by the Company are situated in the rich and generally heavily timbered valley of the Mississippi. Thence to Pine Prairie – or the one hundred and ninetieth mile – we have a large quantity of fertile and valuable prairie and wood land, well adapted for the culture of cane, cotton, corn, &c., and for orchards, stock-farms and country residencies. From Pine Prairie to the Sabine the line of road traverses the heavily timbered pine ridges and hills and the valleys of clear water creeks, peculiar to an upland country. Good cotton lands, an abundance of the best quality of pine timber, sulphur springs and springs of pure water, limestone quarries, clear trout streams and plenty of game, are found here. Many settlements have recently been made and cotton plantations opened, in this section of country, by immigrants from Mississippi, Alabama and Georgia. The land is well adapted for cotton, the only objection being the difficulty and cost of getting the crops to a market. The completion of the road, by remedying this difficulty, will create an active demand for these lands.
   At the time our land lists were being prepared in the General Land Office it was ascertained that lists of high and valuable prairie lands, rightfully the property of the Company, had been, on fraudulent affidavits, selected by the State as swamp land and submitted to the secretary of the Interior and Land Commissioner for approval to the State as such. Timely action on our part arrested the approval of these lists, and further investigation resulted in their being finally approved to our Company. The lands refered to are the most valuable that we have, being, mainly, situated in the high prairies between New Iberia and Opelousas. Most of the land so selected by the State as swamp land was immediately sold by the State Register – improperly and illegally of course – to parties interested in procuring the affidavits, in anticipation of its approval to the state by the United States. It is proper to state here that it is probable that the state officials were unaware of the true character of the lands referred to, and that the witnesses making the affidavits acted in ignorance of the true meaning of the swamp land act. Many, if not all, of the purchasers bought from the state in good faith. The trouble is mainly – if not entirely – due to and the result of the operations of land speculators.
   Many [persons still occupy and cultivate the Company’s lands, thus illegally sold to them by the State Register. Efforts have been made to procure the passage of an act of the Legislature confirming such sales, but it was justly considered that the matter ought properly to be left to the courts.
   Legal proceedings will probably have to be instituted to dispossess the occupants of railroad lands, for their occupation operates seriously against sales to others. It is to be hoped that, on the return of peace, such occupants will come forward and purchase from the Company and thus acquire good titles, and not compel a resort to legal proceedings.
G. W. R. Bayley
Chief Engineer and Land Agent
New Orleans, La.
January 15th, 1863

Home