AR, A&G 2/1/1862 E

Annual Report of the Atlantic & Gulf RR
as of February 1, 1862,
Engineer's Report
 
Atlantic & Gulf Rail Road.
January 25th, 1862
 
Hiram Roberts, Esq.
Acting President
 
Sir,
   At the date of the last Annual Report from this Department, the track was within eight and a half miles of Thomasville, and the expectation was confidently entertained that it would be completed to that place by the middle of February of last year -- but, in consequence of unforeseen difficulties, the most prominent of which was disappointment in obtaining material, the Road was not opened to Thomasville for business until the 16th of April, when the first passenger train arrived there.
   At the commencement of the past year's operations, the force on the Road had been reduced, in consequence of the political embarrassments of the times, from twelve hundred to one hundred and seventy-five hands; the heaviest grading between Thomasville and Bainbridge had, for the same reason, been abandoned, and the prospects for continuing the work were anything but encouraging to the friends of the enterprise.
   But the Directors, with characteristic energy, soon after re-let the whole of the grading between Thomasville and Bainbridge, and the bridging and cross-ties to the first Station, fourteen miles west of Thomasville.
   The result of the year's operations, though not to be compared with that of the two preceding years, will, under all the circumstances, doubtless prove satisfactory to the friends of the Roads.
   At the commencement of the year, only about eight and a half miles of the Road west of Thomasville were graded. Twenty-one and a half miles may be considered complete, if we include Section 47, which will be finished by the 1st of March, leaving fifteen miles yet to be graded.
   The completed Sections are Nos. 44, 45, 46,47, 48 east, 51, 52 east (embracing all of the Section except 1900 feet at west end), 54 and 55 east. The sections yet to be graded are Nos. 48 West, 49 East and 49 West, 50 East and 50 West, 52 West, (1900 feet), 53, and 55 West.
   All of the grading remaining incomplete, is included in Mr. Orr's contract, except 49 West and 50 West. Messrs. King & Austin have contracted to grade the former, and Mr. J. R. Maddox the latter.
   The grading from Thomasville West to the first Station, fourteen miles, is completed continuously, with the exception already alluded to, on Section 47, which will be finished by the 1st of March. The bridging is completed to the same point, and the cross-ties delivered the greater part of the distance, so that the superstructure may be extended to the next Station, whenever it is deemed by the Directors advisable. In this connection, I would call your attention to the recommendation of Mr. Holcomb, in reference to this extension, in his last report.
   In consequence of the blockade, there is no present necessity for it, but when our ports are opened, it will be a matter of considerable importance, both to the company and the planters west of the Ocklocknee river.
   The grading remaining to be done to reach Bainbridge, amounts to 556,500 cubic yards, to complete which during the present year, would require a force of 350 hands. The present force is not more than 200 hands.
   The grading done during the past year amounts to 457,500 cubic yards, and the force employed on graduation, bridging and in getting cross-ties, averaged about 400 hands.
   The following exhibits the amount estimated to contractors during the past year:
January $7,391.00
February 12,241.68
March 19,452.16
April 7,847.18
May 11,180.10
June 9,246.32
July 14,180.37
August 13,110.17
September 28,862.48
October 19,806.12
November 11,466.69
December 10,063.16

Total

$164,847.43
   In the above is included some per centage retained on work done in 1860.
   I submit hereby a statement showing the cost of graduation, bridging, cross-ties, ware-houses, water-stations, road-crossings, frogs, switches, and track laying, on each section of the road from the initial point to Thomasville.
   The Florida Branch, being an enterprise in which your Company must feel a considerable interest, although being built by the Savannah, Albany & Gulf Company, it may not be out of place to mention here, that about fifteen miles of it is graded, eleven miles of it being continuous from the junction. The force employed is about 100 hands. This force will probably be sufficient to complete the grading to the Florida line in July or August of the present year.
Respectfully submitted
J. T. Stone
Chief Engineer

Home