   I have in progress the estimates for the proposed connection of R. Roads at Montgomery, and have instructed the ground to be occupied.
   On reaching Selma and ascertaining the status of the work on the Blue Mountain & Rome Connection I concluded not to volunteer any advice in relation to the progression or suspension of the work. The Company has committed itself to the work so far that an immediate suspension would result in considerable loss. I gave Judge Walker a certificate, addressed to you, for work done and supplies &c furnished, amounting to $60,000. In this, no ??ary was aimed at, or deemed necessary, as the Govt. has a Mortgage on the whole Road. The amount certified to is not however beyond the value of work as fixed in my schedule of prices, and of materials and supplies at present prices. If the bonds are sent to me, please send such form of receipt as the Dept. may require.
   Your dispatch of the 4th has been recd. Genl. Buckner having left Mobile, I shall confer with his successor.
   Your letter of the 2d came to the office during my absence. Capt. Haydon is now at Jonesboro E. Ten. On his return I will consult with him as to the skeleton map of Kentucky & Tennessee. The lumber for the duplicates of Watauga and Holston bridges is now ready, and the framing in progress.
Very Respectfully