| Fla Rail Rd Office |
| Fernandina June 1st 1861 |
| |
| Track laying Estimate No 3 |
| Wm Phelan Contractor |
| |
| Laying track from Statn 6.218 to Statn 6.702 & 31 ft a
distance 9 1/2 miles @ $500 |
47 |
50 |
|
|
| 381 3/4 days extra work @ 1 25/100 per day |
477 |
19 |
|
|
| use of tools |
5 |
09 |
|
|
| No of ties carried forward 220 @ 5 cts |
11 |
00 |
|
|
| |
5243 |
28 |
|
|
| Less reserve of 25 per cent |
1310 |
82 |
|
|
| Amount to your credit |
|
|
3932 |
46 |
|
| |
| I certify the above to be a
correct estimate of the amount of work done by Wm Phelan Contractor for
track laying during the month of May 1860 according to the report of
Assistant Engr O. D. Kensman |
| M. L. Smith |
| Chief Engr F. R. R. |